Disclosed terms
- Active power (Q3 2026)
- Over 1.7 GW (more than 200 MW added in Q3) [1]
- Total contracted power
- Over 4.6 GW (more than 900 MW added in Q3) [1]
- International contracted power
- More than 1.3 GW (including India, Indonesia and Spain) [1]
- Vera Rubin NVL72 milestone
- Multi rack production online for Cognition (company reports 4.8x GB200 NVL72 token throughput) [1]
The disclosure and our analysis
What CoreWeave disclosed in Q3 2026
In its Q3 2026 earnings release filed on Form 8-K on November 10, 2026, CoreWeave said it added more than 200 MW of active power during the quarter to surpass 1.7 GW active, doubling its active footprint since the start of 2026.
Total contracted power rose by more than 900 MW to over 4.6 GW. CoreWeave also reported expanding its international contracted footprint to more than 1.3 GW, including sites tied to India, Indonesia and Spain.
On hardware, CoreWeave disclosed bringing multi rack NVIDIA Vera Rubin NVL72 deployments online, noting first production workloads for Cognition on the platform.
Why company totals do not equal immediate cluster availability
A gap of nearly 3 GW sits between CoreWeave active power (over 1.7 GW) and total contracted power (over 4.6 GW). Contracted megawatts include future halls and landlord built campuses with multi year delivery schedules.
Our public records scorecard tracks individual campuses behind these totals, including Galaxy Helios in West Texas, Applied Digital Polaris Forge 1 in North Dakota, and Core Scientific sites in Denton and Muskogee.
What buyers should verify before signing
Ask which specific campus and building will host your cluster, and whether that hall is already energized or scheduled in a 2027 or 2028 phase.
Confirm what happens to your start date and payment obligations if a landlord hall delivers late, and compare Blackwell availability against early Vera Rubin lead times before locking a multi year commitment.
What remains unknown
The Form 8-K does not break out active megawatts by individual campus, specify whether active power is critical IT or gross power, or publish general availability pricing for Vera Rubin NVL72.
Companies mentioned: CoreWeave, NVIDIA
Sources
- CoreWeave Form 8-K (Q3 2026 earnings release) · Published November 10, 2026
Related pricing guides
WORK THROUGH IT WITH AN ADVISOR
Planning around this news? Talk it through.
Bring your workload, launch date and what could change. We can help you evaluate capacity, compare proposals and identify the deployment support you need.
Related news
Runpod raises Secure Cloud B200 to $8.99 and B300 to $10.49 per GPU hour
Runpod raised on demand Secure Cloud rates for Blackwell GPUs in late November 2026. B200 rose from $7.99 to $8.99 per GPU hour, and B300 rose from $8.99 to $10.49. Community Cloud and Hopper Secure Cloud rates did not change.
Read the analysisNebius Q3 revenue hits $980.8M as 2027 capex plan reaches $12B to $13B
Nebius Group reported $980.8 million in Q3 2026 revenue on Form 6-K, guided to $17B to $20B in preliminary 2027 revenue, and outlined $12B to $13B in 2027 capex largely backed by customer prepayments.
Read the analysisNebius raises GPU prices again October 1; H100 to $4.50, B300 to $9.50
Nebius lists higher on demand GPU prices effective October 1, 2026. H100 rises from $3.85 to $4.50 per GPU hour. H200 rises from $4.50 to $5.40, B200 from $7.15 to $8.50, and B300 from $7.85 to $9.50. This round is 17% to 21%. It is reported to be the second increase since May. [1] [2]
Read the analysis