Warrenton (Vint Hill), Fauquier County, VA
OVHcloud Vint Hill data center (VIN)
Why this stage: A county permit for the Phase 1 data center build-out reached certificate of occupancy status in April 2019, and OVHcloud's FY2025 annual filing reports 39 GWh of energy use at Vint Hill. County permits from 2024 to 2026 show more power lineups, generators and server rows being added inside the existing building. No utility record or megawatt figure was found.
- Owner or developer
- OVHcloud, through its subsidiary Data Center Vint Hill LLC
- OVHcloud's role
- Owner and operator
- Link to OVHcloud
- “OVH Data Center Vint Hill LLC - Land Disturbing Permit” Fauquier County Community Development, permit LDPT-24-024815
- Announced capacity
- “The company is looking to build a second, 120,000-square-foot building on 10.81 acres it bought last summer, according to the county.” FauquierNow data center database (news, used because no county record of the second building was found online)
- Stated timing
- “North America (US - East - Vint Hill) 1-AZ us-east-vin” Source
| Date | Record | What it shows | Source |
|---|---|---|---|
| April 5, 2019 | OccupancyFauquier County Department of Community Development · BLDC-17-006754 | Phase 1 alteration to Data Center at Vint Hill, amended for phase 2 work including medium voltage service, generators, transformers, UPS systems and server modules. Applied March 2017, issued July 2017, finalized April 2019.Status: CO Issued | Record |
| May 9, 2024 | ZoningFauquier County Board of Supervisors · Ordinance on TEXT-24-021435, PCID Overlay District | New special exception rules for large buildings at Vint Hill do not apply to expansions of a data center existing and operating in the district on January 1, 2024, including adjoining parcels under the same ownership. Names no company.Status: Adopted | Record |
| June 11, 2024 | Building permitFauquier County Department of Community Development · LDPT-24-024815 | Land disturbing permit described as OVH Data Center Vint Hill LLC - Land Disturbing Permit, at 6872 Watson Court.Status: Issued | Record |
| September 3, 2024 | Building permitFauquier County Department of Community Development · BLDC-24-025343 | Alteration with amendments for new 400 amp panels and circuits, and lighting, power and outside air for new Phase 5/6 rooms, with rack work for rows V120 and V121.Status: Issued, amended, expires November 2026 | Record |
| May 13, 2025 | Building permitFauquier County Department of Community Development · BLDE-25-026900 | Electrical permit to install 3 new power line ups including switch gear, transformers and generators.Status: Issued, not finaled as of October 5, 2026 | Record |
| January 20, 2026 | Air permitVirginia DEQ, Northern Regional Office · Registration No. 74127 (permit 74127-3) | Permit to Data Center Vint Hill LLC at 6872 Watson Court for 10 emergency diesel generators: four permitted in 2017, five in 2021 and one new in 2026. These are backup units. The permit does not name OVHcloud.Stated capacity: “Kohler Model 2000REOZMD emergency diesel engine gen-sets, 2,923 bhp, 2,000 ekW (each unit)”Status: Issued. Supersedes the permit dated October 6, 2021. | Record |
| March 10, 2026 | Building permitFauquier County Department of Community Development · BLDTD-25-027714 and BLDTD-25-027715 | Two trade permits for new 400A panels, transfer switches and circuits for server rows V120E and F and V121D and E.Status: Issued | Record |
| Undated | Public recordOVH Groupe SA, Universal Registration Document filed with the AMF (France) · FY2025 URD, Appendix 3 environmental data table | Lists Vint Hill as one datacenter directly held by OVHcloud and reports 39 GWh total energy consumption there, PUE 1.36. Names Data Center Vint Hill LLC as a wholly owned subsidiary.Status: Published, fiscal year ended August 31, 2025 | Record |
Unverified: not found in online records
- No utility or SCC record states power capacity for the site. Third-party trackers list 17 to 18 MW, unverified.
- No site plan or building permit was found online for the planned second building on the adjacent land.
- The 2025 power lineup permit and 2026 row permits are issued but not finaled, so it is not confirmed that the new capacity is energized.
- No record says which rows hold GPUs.