Vernon, Los Angeles County, CA
Prime Data Centers LAX01
Why this stage: Per SEC filing. Supermicro's fiscal 2026 annual report says all three tranches of the 21 MW lease commenced by August 15, 2025, and the whole space is subleased to Lambda. That shows the landlord delivered the space. It does not by itself show which GPUs are running there.
- Owner or developer
- Prime Data Centers (4701 Santa Fe, LLC). Super Micro Computer leases the 21 MW and sublicenses all of it to Lambda.
- Lambda's role
- Cloud provider, as sole sublicensee of the leased space
- Link to Lambda
- “the Company entered into that certain Sublicense (the Sublicense) with Lambda, Inc. (the Sublicensee) to sublicense all of the Company's rights and obligations with respect to the Data Center Space.” Super Micro Computer Form 8-K
- Announced capacity
- 21 MW. “the Company has agreed to lease 21 MW of a multi-tenanted facility from the Supplier for a term of 10 years” Super Micro Computer Form 8-K
- Stated timing
- “Lambda will initially lease a portion of the facility representing 21 MW of power.” Source
| Date | Record | What it shows | Source |
|---|---|---|---|
| June 21, 2024 | SEC filingSuper Micro Computer, Inc. · Form 8-K 0001375365-24-000026 | Supermicro leased 21 MW in Vernon from 4701 Santa Fe, LLC for 10 years and sublicensed all of the space to Lambda, Inc.Stated capacity: “the Company has agreed to lease 21 MW of a multi-tenanted facility from the Supplier for a term of 10 years”Status: Filed | Record |
| June 21, 2024 | SEC filingSuper Micro Computer, Inc. · Exhibit 10.2, Service Order MCSA-001 | The service order targeted delivery in tranches on February 1, June 1 and September 1, 2025.Status: Filed | Record |
| August 31, 2026 | SEC filingSuper Micro Computer, Inc. · Form 10-K FY2026, 0001375365-26-000022 | All three lease tranches commenced, each ahead of its target date, and the entire Vernon space is subleased.Stated capacity: “the first tranche of 6 MW having commenced on January 24, 2025, the second tranche of 9 MW commenced on May 12, 2025 and the third tranche of 6 MW commenced on August 15, 2025”Status: Filed | Record |
Unverified: not found in online records
- No City of Vernon building permit or certificate of occupancy was checked. The city website blocked automated reading.
- South Coast AQMD generator permits were not checked.
- No Vernon Public Utilities service record was found online. The operating stage rests on the SEC filing alone.