IBM CLOUD DATA CENTERS

IBM Cloud data centers.
What public records show.

IBM Cloud runs its US GPU servers in leased colocation buildings in its Dallas and Washington DC regions. IBM's own 2026 certificates give the building addresses, and landlord SEC filings and state records confirm the buildings. IBM publishes no company-wide GPU megawatt figure, and no record ties a megawatt figure to IBM's GPUs.

SITES CHECKED OCTOBER 5, 2026

4 IBM Cloud sites.
10 public records.

Each site sits at the highest stage a record supports. Announced megawatts are shown beside the records, never added to them. A missing record does not mean a site is behind. Many counties publish nothing online.

  1. 0Announced
  2. 0Site identified
  3. 2Permitted
  4. 0Power secured
  5. 2Operating

Richardson, Dallas County, TX

DAL12, Digital Realty DFW35 (907 Security Row)

Operating

Why this stage: Per SEC filing. Digital Realty's 2017 10-K says 2016 and 2017 revenue rose from leases of completed space at 907 Security Row. A 2015 TDLR registration names SoftLayer, now IBM Cloud, for an interior build-out in the building. No record states IBM's megawatts here.

Owner or developer
Digital Realty. IBM's 2024 HITRUST letter says DAL12 is managed by Digital Realty. The building owner of record on early TDLR filings is Collins Technology Park Partners LLC.
IBM Cloud's role
Colocation tenant
Link to IBM Cloud
“DAL12 IBM International Business Machines 907 Security Row Richardson, Texas 75081 United States” IBM ISO/IEC 27018 certificate US022526, issued by Bureau Veritas
Announced capacity
“Dallas (us-south) | us-south-dal12-a” IBM Cloud docs, accelerated profile family gen4 (B300)
Stated timing
“NVIDIA HGX B300 accelerated virtual server profiles are available for select customers. Status: Select Availability. Zone us-south-dal12-a.” Source
Public records found for DAL12, Digital Realty DFW35 (907 Security Row), oldest first.
DateRecordWhat it showsSource
September 21, 2015Texas TDLR registrationTexas Department of Licensing and Regulation · EABPRJB6801132Project named SOFTLAYER 907 SECURITY ROW. Interior build-out, estimated cost $460,000, October to December 2015. Owner listed as Collins Technology Park Partners LLC.Status: Project ClosedRecord
December 7, 2015Texas TDLR registrationTexas Department of Licensing and Regulation · EABPRJB6805986DLR 907 Security Row Suite 130. Tenant finish-out of one data center suite with electrical rooms and exterior equipment, estimated cost $16,000,000, November 2015 to April 2016. Names no tenant. IBM's older certificate places DAL12 in Room 130.Status: Project ClosedRecord
March 1, 2018SEC filingDigital Realty Trust, SEC Form 10-K for 2017 · 0001297996-18-000026Revenue increases in 2016 and 2017 came mainly from leases of completed development space, including space at 907 Security Row. Names no tenant.Status: FiledRecord
February 13, 2026SEC filingDigital Realty Trust, SEC Form 10-K for 2025 · 0001104659-26-015365IBM is Digital Realty's fifth largest customer, in 34 locations, with $109.6 million of annualized recurring revenue and a 2.6 year weighted average remaining lease term, as of December 31, 2025. Sites are not named.Status: FiledRecord
Unverified: not found in online records
  • No record states how many megawatts or GPUs IBM runs in this building.
  • No utility or PUCT record for the campus substation was found online.
  • The link between IBM and Suite 130 rests on IBM's 2018 certificate address. The 2026 certificate gives the building only.

Irving, Dallas County, TX

DAL10, QTS Irving campus (DFW1)

Operating

Why this stage: Per SEC filing, now dated. QTS's 2020 10-K describes Irving as an operating facility with 140 MW of utility feeds and leases in place. QTS went private in 2021, so there is no later filing. TDLR shows data hall work at the campus in 2025 and 2026, naming no tenant.

Owner or developer
QTS Data Centers. IBM's 2024 HITRUST letter says DAL10 is managed by QTS.
IBM Cloud's role
Colocation tenant
Link to IBM Cloud
“DAL10 IBM International Business Machines 6341 Longhorn Drive Irving, Texas 75063 United States” IBM ISO/IEC 27018 certificate US022526, issued by Bureau Veritas. QTS's address is 6431 Longhorn Drive; IBM's 2018 certificate used 6431.
Announced capacity
“us-south-dal10-a” IBM Cloud docs, accelerated profile family (gen3)
Stated timing
“IBM lists H100 profiles in zone us-south-dal10-a.” Source
Public records found for DAL10, QTS Irving campus (DFW1), oldest first.
DateRecordWhat it showsSource
February 26, 2021SEC filingQTS Realty Trust, SEC Form 10-K for 2020 · 0001628280-21-003456QTS owns the Irving facility, a former semiconductor plant, and lists leases in place there as of December 31, 2020. Names no tenant.Stated capacity: “the Irving facility has diverse feeds of 140 MW of utility power”Status: FiledRecord
August 6, 2025Texas TDLR registrationTexas Department of Licensing and Regulation · TABS2025025312QTS DFW DH 1.2 6MW. Fit-out of 9,800 square feet for an equipment add in an existing building, September 2025 to October 2026. Names no tenant.Stated capacity: “Fit-out for 6MW equipment add within an existing building”Status: Project RegisteredRecord
September 22, 2026Texas TDLR registrationTexas Department of Licensing and Regulation · TABS2027001697DFW1-DC1-DH1.2, Project Atlas. Adds electrical equipment and hot aisle containment to 9,500 square feet of existing space, estimated cost $2,400,000, October 2026 to July 2027. Names no tenant.Status: Project RegisteredRecord
Unverified: not found in online records
  • The latest SEC operating record is from 2021. No current government record shows the campus operating.
  • No record ties IBM to a specific data hall or megawatt figure on the campus.
  • IBM's 2026 certificate gives 6341 Longhorn Drive. QTS and TDLR use 6431, so this looks like a typo in IBM's document.

Ashburn, Loudoun County, VA

WDC07, Sabey SDC Ashburn (Intergate.Ashburn)

Permitted

Why this stage: Virginia DEQ permits the landlord's backup generators at 21741 Red Rum Drive, most recently in December 2024. The permit names no tenant. No utility approval or operating record was found online.

Owner or developer
Sabey Data Centers, through Intergate - Ashburn, LLC. IBM's 2024 HITRUST letter says WDC07 is managed by Sabey.
IBM Cloud's role
Colocation tenant
Link to IBM Cloud
“WDC07 IBM International Business Machines 21741 Red Rum Drive Suite 2 Suite 4 Ashburn, Virginia 20147 United States” IBM ISO/IEC 27018 certificate US022526, issued by Bureau Veritas
Announced capacity
“Washington DC (us-east) | us-east-wdc07-a” IBM Cloud docs, accelerated profile family gen4 (B300)
Stated timing
“NVIDIA HGX B300 accelerated virtual server profiles are available for select customers. Status: Select Availability. Zone us-east-wdc07-a.” Source
Public records found for WDC07, Sabey SDC Ashburn (Intergate.Ashburn), oldest first.
DateRecordWhat it showsSource
December 3, 2024Air permitVirginia Department of Environmental Quality, Northern Regional Office · Registration No. 73935Authorizes emergency diesel generators at 21741 Red Rum Drive for Intergate - Ashburn, LLC. Adds 43 units for Building A and lists units already permitted at Buildings B and C, including 20 from 2018. These are backup units.Stated capacity: “Forty-two (42) emergency diesel engine gen-sets ... 2,250 kWe”Status: Permit to construct and operate approved. Supersedes the permit of June 3, 2020.Record
Unverified: not found in online records
  • No record shows which Sabey building holds IBM's suites, or how many megawatts IBM uses.
  • No government operating record or utility approval was found online.
  • Sabey is private, so no SEC filing describes delivery at this campus.

Ashburn, Loudoun County, VA

WDC06, NTT VA2 and VA4 (Guilford Drive and Gigabit Plaza)

Permitted

Why this stage: Virginia DEQ permits the landlord's backup generators at both addresses IBM lists for WDC06: VA2 in 2016 and VA4 in a 2025 campus permit. Neither permit names a tenant. No utility approval or operating record was found online.

Owner or developer
NTT Global Data Centers, formerly RagingWire. IBM's 2024 HITRUST letter says WDC06 is managed by Raging Wire.
IBM Cloud's role
Colocation tenant
Link to IBM Cloud
“WDC06 IBM International Business Machines 44610 Guilford Drive Suite 4 Suite 7, 44760 Gibabit Plaza VA4 Ashburn, Virginia 20147 United States” IBM ISO/IEC 27018 certificate US022526, issued by Bureau Veritas
Announced capacity
“us-east-wdc06-a, us-east-wdc07-a” IBM Cloud docs, accelerated profile family (gen3)
Stated timing
“IBM lists H100, H200 and Gaudi 3 profiles in zone us-east-wdc06-a.” Source
Public records found for WDC06, NTT VA2 and VA4 (Guilford Drive and Gigabit Plaza), oldest first.
DateRecordWhat it showsSource
January 13, 2016Air permitVirginia Department of Environmental Quality, Northern Regional Office · Registration No. 74094Authorizes 13 diesel emergency generators at RagingWire VA2 Data Center, 44610 Guilford Drive. These are backup units.Stated capacity: “Thirteen (13) Cummins QSK60-G14NR2 model diesel engine emergency gen-sets 2,250 kW”Status: Permit to construct and operate approvedRecord
July 11, 2025Air permitVirginia Department of Environmental Quality, Northern Regional Office · Registration No. 74120Authorizes emergency diesel generators at NTT buildings VA3 to VA7 on Gigabit Plaza, including VA4 at 44760 Gigabit Plaza. These are backup units.Status: Permit to construct and operate approved. Supersedes the permit of November 17, 2022.Record
Unverified: not found in online records
  • No record states IBM's megawatts or GPU count in VA2 or VA4.
  • No utility approval or government operating record was found online.

NOT YET CHECKED

Other IBM Cloud sites.

These sites are named by the company or its partners. We have not yet checked their public records.

  • Together AI B300 clusterUnnamed IBM Cloud location

    IBM announced a $240 million multi-year deal on August 11, 2026 for a large HGX B300 cluster with expected availability in Q1 2027. No site, megawatts or GPU count named.

  • DAL13, CyrusOne Carrollton1649 W Frankford Rd, Carrollton, TX

    IBM lists this Dallas zone in its 2026 certificates. IBM's GPU profile docs reviewed do not list it for GPUs.

  • DAL14, STACK Plano6715 Pinecrest Dr, Plano, TX

    IBM opened DAL14 as its fourth Dallas zone. TDLR shows STACK data center projects at this address. IBM's GPU profile docs reviewed do not list it for GPUs.

  • WDC04, Digital Realty Digital Loudoun Plaza44060 Digital Loudoun Plaza, Ashburn, VA

    IBM's earlier certificates list WDC04 here. IBM's GPU profile docs reviewed do not list it for GPUs.

  • IBM Quantum Data CenterPoughkeepsie, NY

    IBM plans a 511,000 square foot quantum facility at its own campus. News reports a county IDA preliminary approval in September 2026. Quantum, not GPU, so not researched here.

BEFORE YOU SIGN

Ask which site
backs your quote.

Company totals do not tell you whether your allocation is live. These questions tie a proposal to a site you can check.

  1. Which zone will host my GPUs? IBM lists B300 only in us-south-dal12 (Richardson, Texas) and us-east-wdc07 (Ashburn, Virginia).
  2. IBM marks B300 as Select Availability. How many GPUs are free in my zone today, and will you commit a delivery date in writing?
  3. Is the Together AI B300 cluster due in Q1 2027 going into the same zone as my capacity, and could it limit power or space for me?
  4. IBM leases these buildings. Digital Realty reports a 2.6 year average remaining lease term for IBM. What happens to my workload if a lease ends or a hall must move?

WORK THROUGH IT WITH AN ADVISOR

Check a IBM Cloud proposal against the record.

Bring your workload, launch date and what could change. We can help you evaluate capacity, compare proposals and identify the deployment support you need.

Discuss my project ↗

Notes on these records

  • IBM's 2025 10-K gives no data center count or megawatts. It reports about 17 million square feet of US facilities, about 9 million leased, used partly for cloud centers, and about $314 million of lease payments not yet commenced.
  • IBM is Digital Realty's fifth largest customer, in 34 locations, per Digital Realty's 2025 10-K.
  • Site addresses come from IBM's own 2026 Bureau Veritas certificates. Landlord names come from IBM's July 2024 HITRUST letter, published on IBM's website.
  • No IBM filing mentions Together AI or GPUs. The $240 million deal appears only in IBM's press release.

Records were read online on October 5, 2026. Corrections are welcome through the form below. All providers ↗

WHY WORK WITH US

Powered by
Bridgepointe Technologies.

GPU Cloud Advisors is powered by Bridgepointe Technologies, a technology advisory firm since 2002. You get one advisor, the research on this site, and the provider relationships behind it.

Bridgepointe clients include

  • NVIDIA
  • Salesforce
  • Adobe
  • Uber
  • Netflix
  • Airbnb
  • Roblox
  • LinkedIn
  • CrowdStrike
  • Sony
  • PayPal
  • Mastercard

75+ Fortune 500 clients

Including more than 20 of the Fortune 100, with 97% client satisfaction.

1,200+ data center and cloud projects

Requirements assessed, capacity sourced and providers selected.

Terms, not just the rate

We negotiate ramp schedules, early billing and expansion terms, so you aren’t paying for capacity before your workload can use it.

One requirement, every fit

Bridgepointe partners with 380+ technology providers. We take one requirement to the providers that fit it and bring back a side-by-side comparison you can actually decide from.

Case study: Bridgepointe helped Hive, an AI company, choose data center and connectivity providers across 15 projects, saving its team at least 180 hours. Ask us for the case study

LET’S PLAN YOUR GPU PROJECT

Tell us what
you need.

Two short steps. Tell us what you’re building and an advisor will help you evaluate providers, confirm capacity requirements, and plan the support you need to get into production.

Not sure which GPU or how many you need? Start with your workload and what could change.

Our advisory services are free to you. We’re compensated by whichever provider you choose through us.

No obligationSizing help welcome
What we’ll work through with you
  • A provider shortlist suited to your workload and location.
  • Initial capacity, expansion needs and delivery timing to confirm.
  • Total cost, commitment terms and deployment support to compare.
Step 1 of 2What you need

Include GPU type, quantity and likely growth if known. A rough outline is enough.