Douglasville, Douglas County, GA
ATL1 at Flexential Atlanta-Douglasville
Why this stage: Georgia issued the landlord, Flexential, air permits for backup generators at the campus in 2025 and 2026. They do not name DigitalOcean. DigitalOcean's annual report says it leases data centers in the Atlanta area but does not name this site or say it is energized, so we do not count it as an operating record.
- Owner or developer
- Flexential
- DigitalOcean's role
- Colocation tenant
- Link to DigitalOcean
- “Flexential's Douglasville facility addresses our need to bolster GPU infrastructure quickly as our AI/ML business continues to grow” Flexential press release, quoting DigitalOcean
- Announced capacity
- 9 MW. “Two data halls, each offering 4.5 MW of power (9 MW total)” DigitalOcean blog
- Stated timing
- “DigitalOcean's GPU availability page, updated August 10, 2026, lists H200, MI300X, MI325X and MI350X GPUs in ATL1.” Source
| Date | Record | What it shows | Source |
|---|---|---|---|
| April 25, 2025 | Air permitGeorgia EPD, Air Protection Branch · Permit 7374-097-0100-S-01-0 | Permit to Flexential at 1700 North River Road for eight new diesel emergency standby generators at an existing data center, for a total of 21. These are backup units. It does not name DigitalOcean.Status: Issued | Record |
| February 24, 2026 | SEC filingDigitalOcean Holdings, Form 10-K for 2025 · 0001582961-26-000019, Item 1 (Atlanta) | DigitalOcean says it leases data centers in the New York, San Francisco and Atlanta metropolitan areas and plans new facilities in 2026 in Memphis, Richmond and Kansas City. No landlord or megawatt figure is given per site.Status: Filed | Record |
| May 5, 2026 | Air permitGeorgia EPD, Air Protection Branch · Permit amendment 7374-097-0100-S-01-1 | Authorizes 33 more diesel emergency standby generators, for a total of 54 across buildings ATL05 and ATL06. These are backup units. It does not name DigitalOcean.Stated capacity: “2.5 MW Emergency Generator (most units listed); 2.74 MW Emergency Generator (24 units at ATL06)”Status: Issued | Record |
Unverified: not found in online records
- No government record names DigitalOcean at the campus. The tenant link comes from DigitalOcean and Flexential announcements.
- No utility or energization record was found online.
- No record confirms the second 4.5 MW hall is live. DigitalOcean planned it for 2025.